Agribusiness project appraisal and evaluation UE Past Papers Questions.
View All Courses |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
(2211) Question Category: Mathematical Calculation A company has a cost of capital of 10% as investment opportunity and estimated cash flows are shown in Table below.
Answer / Solution UNSOLVED |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(2619) Question Category: Long answers Suppose a potential investor approaches you to assess the worthness to invest his money in dairy production
Answer / Solution UNSOLVED |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(2924) Question Category: Mathematical Calculation Study the following data for the purpose of assessing the project`s viability. All figures are in Million TShs.
Required
Answer / Solution UNSOLVED |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(2925) Question Category: Short answers Consider the following situation. Two hectares farm project is about to start by putting 15mm wire fence on its entire perimeter. Water needed for making the concrete for fixing fencing poles is essentially rerquired to be obtained from the bore hole that will be dug in the same farm. The first activity is digging the 75cm deep holes for whole farm perimeter. The need for water for making concrete for fixing the poles arises only after the digging of the holes is completed. The fencing poles will be placed at an interval of 2 meter. Only one labourer is available and he is tasked to dig 10 holes per day. The second activity of digging water bore hole will be doneby two highly experienced labourers who have promised to finish the job for exactly 15 days. The project manager has agreed that all these two activities to be done concurrently so that by the time digging holes is completed, placing the fencing pole and fixing fence wire start. Then two (2) days will be needed for quality assurance team to the fence before handling over the project ,. From these scenarios you are required to:
Answer / Solution UNSOLVED |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(2926) Question Category: Long answers
Answer / Solution UNSOLVED |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
News & Updates | Recently
Recent Updates |
---|
2024-05-02: questionsQuestions Uploaded on 2024-05-02 |
2024-03-29: questionsQuestions Uploaded on 2024-03-29 |
2024-03-19: questionsQuestions Uploaded on 2024-03-19 |