Operations research UE Past Papers Questions.


View All Courses

(2365) Question Category: Short answers

Using some economic theories, briefly explain the following

  1. The coefficient of slack variables equal zero in the objective function
  2. The basic variables in the initial simplex tableau are the slack variables
  3. In the simplex method of solving L.P problem, the variable with the largest positive C_{j}-Z_{j} value is the entering variable. Give its economic rationale.

Answer / Solution

UNSOLVED

(2597) Question Category: Mathematical Calculation

The HC & AC Ltd makes two kinds of tables-end tables(X1) and coffee tables(X2). The manufacture is restricted by material and labor constraints, as shown in the following linear programming formulation.

Maximize Z=200x_{1}+300x_{2}(profit,$)

Subject to

egin{align*} 2x_{1}+5x_{2} leq 180(labor hr)\ 3x_{1}+3x_{2}leq 135(wood, ft)\ x_{1}, x_{2}geq0 end{align*}

The final optimal simplex tableau for this problem is as follows:

C_{j} 200 300 0 0
  Basic variables Quantity X1 X2 S1 S2
300 X2 30 0 1 1/3 -2/9
200 X1 15 1 0 -1/3 5/9
  Z_{j} 12,000 200 300 100/3 400/9
  C_{j}-Z_{j}   0 0 -100/3 -400/9
             
  1. Formulate the dual for this problem
  2. Prove that the shadow price for labor hour is $100/3
  3. What is the importance of the duality theory to the agribusiness managers?

Answer / Solution

UNSOLVED

(2598) Question Category: Short answers

  1. Why do waiting lines form at a service facility even though there may be more than enough service capacity to meet normal demand in the long run?
  2. What are the assumptions and limitations of the Queuing theory?

Answer / Solution

UNSOLVED

(2599) Question Category: Mathematical Calculation

  1. Using vivid examples , distinguish between a transportation model and assignment model.
  2. A concrete company transports concrete from three plants to three construction sites. The supply capacities of the three plants, the demand requirements at the three sites and the transportation costs per ton are as follows.
Construction site
Plant A B C Supply(tons)
1 $8 $5 $6 120
2 15 10 12 80
3 3 9 10 80
Demand(tons) 150 50 100  

Determine the linear programming model formulation for this problem and find the initial optimal solution using the Minimum Cost (MCC) method.

Answer / Solution

UNSOLVED

(2708) Question Category: Short answers

Briefly describe the management science approach to problem solving.

Answer / Solution

UNSOLVED


View All Courses
News & Updates | Recently
Recent Updates
questions

2024-05-02: questions

Questions Uploaded on 2024-05-02


questions

2024-03-29: questions

Questions Uploaded on 2024-03-29


questions

2024-03-19: questions

Questions Uploaded on 2024-03-19

Dismissible in 10 seconds